Utility · Maryland
WSSC Water: Usually WSSC to the property line; some single-family taps are the owner's entire pipe
WSSC Water serves Montgomery County and Prince George's County. Its customer FAQ says WSSC maintains the sewer lateral from the main to the property line, and the homeowner maintains the line from the property line to the house. A different WSSC page says that for a single-family connection built from an existing main, WSSC maintains the tap only and the rest of the service pipe is the owner's. You need to know which kind of connection you have.
Last verified against the official pages listed below. If a number is not on those pages, it is not on this one.
- Property owner
- Utility or city
- Not assigned by the page we read
Open this place in the checker WSSC Water
The FAQ's property line is the usual case, not the only case
WSSC's customer service FAQ answers "what portion am I responsible for?" directly. Generally, the contractor who installed the main also installed the service from the main to the property line. WSSC maintains that individual sewer service from the main to the property line. The service line from the property line to the house, and the pipes inside the house, are the homeowner's. That is the sentence most people are handed, and it is on the official FAQ.
The service-connections page for private property adds the exception. For connections built with a mainline extension, the service connection in a WSSC right-of-way extends to the right-of-way or the property line, whichever is closer to the main, and WSSC maintains the portion it constructed. For a connection built from an existing main, Maryland law since July 1, 1999 requires the applicant to build the service connection, except where the development is one single-family house. For that one house, the master plumber exposes the main and WSSC makes the tap. The page then says there is no service-connection pipe length for WSSC to install or maintain. WSSC maintains the tap only. All of the service pipe is the property owner's.
The 2024 code measures the owner's pipe to the closer of three lines
The 2024 WSSC Plumbing and Fuel Gas Code, effective December 1, 2025, section 102.3.3, says the property owner maintains building water and sewer services from the building to the service connection located at the property line, the edge of the public right-of-way, or the edge of an easement and right-of-way granted to the commission, whichever is closer to the building. Section 102.3.2 says the commission maintains its mains, service connections, meters, and appurtenances. Read those two subsections together with the single-family tap exception. "Service connection" is not always a long pipe. Sometimes it is the tap.
Section 102.3.6 is the stoppage rule. The owner, at the owner's sole expense, hires a WSSC-licensed master plumber or a WSSC-licensed sewer and drain cleaner to clear the stoppage from the building to the commission's main. If the stoppage was caused by a defective building sewer, or by a defective joint between the private sewer and the commission's service connection, the owner hires a WSSC-licensed master plumber to fix it. Stoppages in commission mains are the commission's. If a cleaner cannot relieve a hard or soft stoppage in a defective service connection, the commission relieves or corrects it without a backcharge to that cleaner.
Ask which connection you have before you accept a street bid
A house on a newer main extension and a house tapped off an older main can sit on the same block and have different owners for the pipe under the road. The FAQ's property-line rule and the private-property page's tap-only rule are both WSSC documents. The one that applies is the one that matches how the service was built. WSSC can say which one an address is. A plumber guessing from the FAQ alone can be wrong in either direction.
The code also says enforcement of the off-property stoppage sections sits with the Utility Services Division, not the Regulatory Services Division. If you are arguing about a pipe in the right-of-way, that is the office named in section 102.3.7. Nothing on these pages is a point-of-sale certificate or a published repair rebate. We did not add one.
Before you call WSSC Water
- Ask WSSC whether your service was built with the main or tapped later for a single house. The maintained length is different.
- For a stoppage, hire a WSSC-licensed master plumber or sewer and drain cleaner. The code puts that cost on the owner from the building to the main.
- If the cleaner cannot clear a defective service connection, the code says the commission corrects it without backcharging the cleaner.
- Use section 102.3.3's "whichever is closer to the building" test when the property line and the right-of-way edge are not the same line.
Stoppages follow a third rule. The plumbing code says the owner pays a WSSC-licensed plumber or drain cleaner to clear a stoppage from the building to the commission's main, even when part of that length is a commission pipe.
The comparison table puts this split next to the other places we have sourced. The method explains why a city with no page is left out.
Rules that do not match WSSC Water
- Washington, D.C.: DC Water maintains pipes to the property line; clog clearing starts with the owner.
- Fairfax County: County maintains the public main; the backup page includes the connection in the owner's line.
- Alameda: Owner maintains the upper lateral; the city maintains the lower.